We design and supply boiler piping and heat exchangers.
References
Gas boiler-rooms (project documentation)
Project documentation was provided by IVITAS for the issuance of a building permit, engineering and processing of all-cost project documentation for the construction of two gas boiler rooms in the premises of IVECO Czech Republic in the Czech city of Vysoke Myto.
Project documentation for steam pipeline at the TAMEH heating plant
In connection with a modernization project for energy operations at the TAMEH heating plant, IVITAS delivered project documentation for implementing the connection of an output steam pipeline from the No. 3 to No. 2 high-pressure steam distributor.
Assessment of flue gas boiler
We were contracted by our client CS Cabot to assess problems they were experiencing with a flue gas boiler, which has a heat output of 8.25 MW. The heated flue gases utilized by the boiler come from the production of soot.
Flexibility analysis of steam pipelines for CEZ Prunerov Power Plant (EPR II)
We prepared a flexibility analysis of superheated steam pipelines at the EPR II power plant units for our client CEZ Energetické produkty. The purpose of the analysis was to verify the settings of individual spring hangers, including recommended measures for bringing them into their working areas.